Soho

Location

W1

Project Duration

3 Weeks

Area

136LM

Project Type

Internal back painted glazing

Project Overview & Challenges

Soho, Central London – Our client required internal back painted glazing to all columns, soffits and stair locations horizontally over 3no levels. Each section was surveyed and designed within a 6day turnaround due to the client’s delivery expectation. Glass was procured and installed within 2weeks. All vertical and horizontal access was supplied by ourselves via scaffold.

Project Gallery